EL FLORIDO SUBSTATION

18 June, 2022

PLACE: EJIDO OJO DE AGUA, TIJUANA, BC.

WE WERE PART OF THE MODERNIZATION PROJECT OF THE CFE EL FLORIDO SUBSTATION, IN TIJUANA B.C., OUR TEAM WAS IN CHARGE OF RECEIVING AND REVIEWING IN DETAIL A NEW TRANSFORMER OF 20MVA AND PRIMARY VOLTAGE OF 115KV, INSTALLING IT AND LEAVING IT IN OPTIMAL CONDITIONS FOR ITS CORRECT OPERATION PERFORMING VARIOUS TESTS LIKE; POWER FACTOR, WINDING RESISTANCE, EXCITATION CURRENT, OIL TESTS, RESISTIVITY, CHROMATOGRAPHY, AMONG OTHERS.