RECALIBRATION AT LORETO SUBSTATION, BAJA CALIFORNIA SUR
15 June, 2022
PLACE: LORETO, BCS.
WE CARRIED OUT THE CONSTRUCTION OF THE OVERHEAD LINE AND RECALIBRATION OF THE EXISTING LINE OF THE LORETO SUBSTATION FOR CIRCUIT 4135 AND 4155.
THE NEED ARISED TO IMPROVE TWO CIRCUITS OF THE POWER SUBSTATION, FOR THIS USE WE RECALIBRATED TWO CIRCUITS OF THE SAME PATH. NEW POSTS WERE INTERSpersed AND THE EXISTING ONES WERE RESTRUCTURED TO INSTALL 24KM OF NEW CONDUCTOR IN A DOUBLE CIRCUIT NETWORK TO COMBAT THE LOSSES OF THE SUBSTATION.