WE BUILT THE OVERHEAD LINE IN SEVERAL COMMUNITIES IN THE MUNICIPALITY OF LORETO (CALLE SIERRA, CERRO SAN JUAN, CALLE B PROLONGATION, SANTA GERTRUDIS AND AQUEDUCT). THIS PROJECT HAD THE PURPOSE OF IMPROVING THE QUALITY AND LOSS OF ENERGY IN THE CITY, TO DO THIS WE INSTALLED 20 POLES, 5 TRANSFORMERS AND ONE KM OF CONDUCTOR OF DIFFERENT CALIBERS TO STABILIZE THE CIRCUITS OF THE CITY.